Many of you will recognise this quotation from the BBC’s
‘Blackadder’ comedy series. Many of you may
also be aware of the Society of Construction Law’s
‘Delay and Disruption Protocol’. A few of you
may know that one of the lynchpins of the protocol is the
contractor’s approved programme prepared in ‘critical
path method’ format. The protocol goes on to explain
how this programme is used to quantify extensions of time
for which the contractor may be entitled as a result of
delaying events. The measuring tool for this is the approved
programme.
The focal point of this article is the approved programme,
or ‘baseline’ programme as it is often called.
First of all, a few basics.
What is Planning and Why Have a Programme?
Before you prepare a programme, you must have a plan. On
a construction project, ‘planning’ covers all
aspects from overall planning, such as building ‘A’
must be completed before building ‘B’ can start,
down to detailed planning, such as the activity ‘Excavate
for Foundations’ has to be completed before is successor,
‘Pour Concrete in Foundations’ can start.
By planning the works in detail, and linking activities
in a logical manner, a contractor creates a network of activities
and their dependencies or inter-relationships as shown above.
If this is done in a proper manner encompassing all works
and all restraints on the project, then this is the basis
for a critical path network (CPN).
The next stage is to calculate the time each activity will
take. This phase is the start of preparing the programme
for the project. For example, for ‘Excavate for Foundations’,
the contractor will know he has 1,000 cubic metres of soil
to dig out, and at a productivity rate of 100 cubic metres
per day this activity will take 10 days. This is known as
the activity’s ‘duration’.
After completing this exercise for all activities, he then
has a ‘time frame’ for the project. For example,
‘Excavate for Foundations’ will start on day
1 and because it has duration of 10 days, it will finish
on day 10. It’s successor, ‘Pour Concrete in
Foundations’, will start on day 11 and as it has a
duration of, lets say 15 days, will finish on day 26. The
contractor now has a programme.
What is the use or benefit of a programme?
By preparing a programme in the above manner, a contractor
reassures himself that he can complete all the works and
achieve completion by the project by the Contract completion
date. He knows when he has to have available key resources
or equipment. Using the above simple example, he knows that
he is going to ‘Pour Concrete in Foundations’
starting on day 11, therefore he will have to have his concrete
producing equipment up and running by this date.
The benefit of a programme for the employer or Contract
Administrator is that they are also reassured that the contractor
can complete the project on time, and that he has planned
the works in a reasonable and logical manner. Again using
the above example, the engineer knows at an early date that
the contractor intends to start ‘Pour Concrete in
Foundations’ on day 11 and that he has to provide
the drawings for this work before this date.
Why is the programme updated?
The programme is also important after the project has started.
At regular intervals, say monthly, the programme is updated.
That is to say the progress achieved on each activity on
the programme is recorded. A ‘time analysis’
of this progress information will show if the contractor
is either ahead or behind programme, and it will calculate
new start and finish dates for all remaining activities.
For example, if the contractor is making good progress on
‘Excavate for Foundations’, then the new start
date for ‘Pour Concrete in Foundations’, will
be (say) day 7. If he is making poor progress, then the
new date for this activity will be (say) day 15. By carrying
out this updating at regular intervals, both the contractor
and engineer are alerted to the changing requirements, or
new ‘need-by’ dates for information, etc on
the project.
In the SCL’s protocol, the contractor’s programme
is a very important document.
In my experience, the contractor’s initial (or baseline)
programme is often poorly prepared. On some occasions, I
have seen programmes where every activity is critical with
no float – which would result in an EOT entitlement
from even a small variation order (hence, the title of this
article!).
Before demonstrating entitlement to an EOT and quantifying
its extent, the programmes reasonableness must be established.
If the good practice in the SCL’s protocol has been
followed, then the Contract Administrator will have been
given the necessary supporting information to establish
that the programme was workable
Roger Gibson (November 2002)
|