Gibson Consulting Limited, 3 The Quadrant, Coventry CV1 2DY  T:024 7624 3607  F:024 7624 3608
 
Sunday Lunch

The critical path is the series of activities which represent the shortest time in which a project or task can be completed. It is identified and calculated by following the logic links between the various activities. Nowadays, there are many planning software packages that carry out this exercise in a matter of seconds.

However, we would like to explain and demonstrate by the use of a few graphic charts the development of a simple programme, its critical path and the float on non-critical activities. For this demonstration we have chosen an ordinary task and called it ‘The Sunday Lunch’; and associated this with the development of a programme and critical path for a construction project.

On a particular Sunday, the ‘Gibson family’, want to have their Sunday dinner before watching their favourite football team, Melchester Rovers, on TV at 2pm.

The first chart, fig. 1 below, shows the ‘Family’s Desire’, which we have related to being ‘The Contract’ on a construction project.

The next chart, fig. 2, is the ‘Menu’. This can be associated with ‘The Design’ on a construction project.

Things now start to develop and the next chart, fig. 3, is titled ‘Mum’s Instructions’. This is the development of the ‘Menu’ (or ‘Design’), and can be associated with using the ‘Specifications’ on a project.
‘Now the Activity Begins’, is the title of the next chart, fig. 4 below. This is where ‘The Contractor goes to work’, and plans what needs to be done.
Figure 5 below, is a graphic representation of the planned activities as listed in Fig.4. The activities are all consecutive, and broadly speaking, represent the Critical Path to complete the Sunday Dinner to enable the Gibson family to watch football on TV, in accordance the ‘Family’s Desire’, in fig. 1. At this stage you will note that there are no time periods or durations on the activities.
At this stage the plan needs to be scheduled. To do this we need to, A) assign time to the activities, and B), look at the resources available. Figure 6 below, shows how long each of the tasks will take. As you will see two of the tasks on fig.5, ‘Cook Food’ and ‘Serve & Eat’ have been expanded into other activities. For example, ‘Cook Food’ has now been expanded into, ‘Roast Beef’, ‘Potatoes’, Green Beans’, ‘French Bread’ and ‘Mr. Gibson’s Frozen Lemon Pie’. Each of these activities has a different time period or duration.
Figure 7 below, shows the resources that are available to carry out the ‘Cook Food’ activities.
The next chart, figure 8, is titled ‘The Programme’, and can be aligned to a typical ‘Contractor’s As Planned Programme’. As you can see, the tasks or activities now have logic links between them. For instance, ‘Mum’s Okay’, follows the preparation and completion of the ‘Shopping List’. You will also note that the five number ‘Cook Food’ activities can be carried out in parallel, and are therefore concurrent.
On the next chart, fig. 9, we have highlighted the Critical Path. This is the shortest time that all the tasks or activities can be completed, and as you can see in the ‘Cook Food’ activities, the Critical Path runs through the ‘Cook Roast Beef’ activity, which has a time period, or duration, of 90 minutes.

You will also see from the above chart, that the four other ‘Cook Food’ activities have a lesser duration than ‘Cook Roast Beef’. For example, ‘Prepare/Cook Potatoes’ has a duration of 30 minutes, which is 60 minutes less than the ‘Cook Roast Beef’ activity. This means that ‘Prepare/Cook Potatoes’ can be started up to 60 minutes later than ‘Cook Roast Beef’, without delaying the overall completion of the Gibson family’s ‘Sunday Dinner’, in time for them to watch their favourite football team, Melchester Rovers, on TV at 2pm. This 50 minute period of time is known as ‘float’, i.e. the period of time an activity can be delayed without affecting the project end date.

The as planned programme is fine, but similar to what occurs on a construction project, actual events may or may not affect the completion, i.e. the Gibson family sitting down to watch TV at 2 p.m. Lets look at what happens.

Before starting the cooking phase, ‘Mum’ changed her mind on the potatoes, she decided that instead of new potatoes she was going to have roast potatoes. In effect, a ‘variation’, similar to what happens on a construction project. The roast potatoes will take an extra 20 minutes to cook, but as explained in 12 above, ‘Prepare/Cook Potatoes’ has a float of 60 minutes. Therefore, this change can be accommodated in the programme without delaying the completion time. The critical path in the ‘Cook Food’ activities remains through the ‘Cook Roast Beef’. See fig. 10 below.

The next event that happens, is that during the Cooking phase, when cooking is in progress with the Roast Beef, Potatoes and Beans, but before cooking of the Lemon Pie starts, Dad decides that he wants the Roast Beef cooked ‘well done’. This will take a further 30 minutes, and as this activity is on the critical path, it will cause a delay to completion of the meal. Mum declares that as Dad made the change, then he is responsible for the delay in completing the meal, and sitting down to watch TV 30 minutes late. See figure 11 below.
But this is not the end of it. Twenty minutes after Dad changed the roast beef to being cooked well done, Mum takes the Lemon Pie from its container and notices that the Pie is mouldy. Its ‘use by date’ expired six months ago. To go and buy a new Pie will take 40 minutes and will cause a further 20 minute critical delay to completion of the ‘Sunday Lunch’. Dad blames Mum for this delay. This subsequent delay is concurrent with the Dad’s delay to the Roast Beef. See fig. 12 below.
© Gibson Consulting Ltd 2001-2003