|
It’s vital to know the difference
between good planning
and too little or too much planning”.
Not enough planning allows the process of construction to
get unruly and take on a lift of its own. Too much planning
stifles the ability to adapt to changing conditions. Good
planning allows the project’s manager (e.g. contractor)
to have a game plan and impose order and adapt to the often
chaotic process of construction.
These are our beliefs based on our experience; but first
let’s define ‘planning’ and ‘programming’.
These two terms are often misused.
Before you prepare a programme, you should have a plan. Planning
involves detailed consideration of all the activities to complete
the project; realistic estimates of how long each activity
will take; and relationships, or dependant logic, between
activities. On a construction project, ‘planning’
covers all aspects from overall planning, such as building
‘A’ must be completed before building ‘B’
can start, down to detailed planning, such as the activity
‘Excavate for Foundations’ has to be completed
before is successor, ‘Pour Concrete in Foundations’
can start. By planning the works in detail, and linking activities
in a logical manner, a Contractor creates a network of activities
and their dependencies or inter-relationships as shown in
the above example. If this is done in a proper manner encompassing
all works and all restraints on the project, then this is
the basis for a critical path network; often referred to as
a ‘CPM’.
The next stage is to calculate the time each activity will
take. This phase is the start of preparing the programme,
or the ‘programming’ aspect, for the project.
For example, for ‘Excavate for Foundations’, the
Contractor will know he has 1,000 cubic metres of soil to
dig out, and at a productivity rate of 100 cubic metres per
day this activity will take 10 days. This is known as the
activity’s ‘duration’. After completing
this exercise for all activities, he then has a ‘time
frame’ for the project. For example, ‘Excavate
for Foundations’ will start on day 1 and because it
has duration of 10 days, it will finish on day 10. It’s
successor, ‘Pour Concrete in Foundations’, will
start on day 11 and as it has a duration of, lets say 15 days,
will finish on day 26. We now have a programme.
What is the use or benefit of a programme?
By preparing a programme in the above manner,
a contractor reassures himself that he can complete all the
works and achieve completion by the project by the project’s
completion date. He knows when he has to have available key
resources or equipment. Using the above simple example, he
knows that he is going to ‘Pour Concrete in Foundations’ starting on day 11, therefore he will have to have his concrete
producing equipment up and running by this date.
The benefit of a programme for the client or contract administrator,
is that they are also reassured that the contractor can complete
the project on time, and that he has planned the works in
a reasonable and logical manner. Again using the above example,
the design team knows at an early date that the contractor
intends to start ‘Pour Concrete in Foundations’ on day 11 and that they have to provide the drawings for this
work before this date.
A programme is also important after the project has started.
At regular intervals, usually monthly, the programme is updated.
That is to say the progress achieved on each activity on the
programme is recorded. By carrying out a ‘time analysis’,
and the contractor is either ahead or behind programme, new
start and finish dates will be created for all remaining activities.
For example, if the contractor is making good progress on
‘Excavate for Foundations’, then the new start
date for ‘Pour Concrete in Foundations’, will
be day 7. If he is making poor progress, then the new date
for this activity will be day 15. By carrying out this updating
at regular intervals, the contractor, client and design team
are alerted to the changing requirements, or new ‘need-by’ dates for information, etc on the project.
A programme is very useful in supporting an entitlement to
an extension of time.
(see ‘extensions of time’)
How can we help you?
Gibson Consulting can provide you with any of the following:
Master
Planning
This is the creation of the overall project plan. First,
we draft a preliminary plan, based on your requirements;
e.g. financial milestones, planning approvals, construction
start and, very importantly, construction completion and
delivery. The second stage is to meet and discuss the preliminary
plan with your project team, i.e. your design consultants,
construction manager, and/or project manager. The objective
of these discussions is to expand the preliminary plan into
a fully integrated master plan for the project incorporating
the work and tasks of the design team.
A major development of the master plan should take place
after appointment of the contractor. His detailed construction
schedule and design requirements should be incorporated
into the master plan. You will then have a comprehensive
plan for the project to achieve your delivery date and all
parties should confirm, or ‘buy-into’, the master
plan as being accurate and realistic. In essence, the master
plan will identify and co-ordinate the contractor’s
and design team’s requirements and deliverables in
order to achieve your delivery date.
Tender Planning
We can provide tender planning, prepared from drawings,
specifications, schedules of work or bills of quantities.
This will assist you with your tender preparation, and the
resulting programme can accompany your tender submission.
Alternatively, Contractor’s programmes can be considered
and advised upon.
Detailed
Planning & Programming
The principle function of detailed planning and programming
is to clearly show the execution of the works and the efficient
deployment of resources so that the contract requirements
and cost objectives are met. In our experience, the best
way of doing this is to create a network, commonly known
as a critical path method (CPM) programme.
The CPM programme required to be carefully composed to enable
both the Contractor and Employer to monitor the execution
of the works. When changes arise the CPM provides the basis
for making decisions which are consistent with the contract
and cost requirement.
Design & Information Planning
Key tools in the success of a project are the preparation
and adherence to (i) a design programme, and (ii) an information
requirement schedule. Essentially, these co-ordinate the
input of architects, engineers and designers with the Contractor’s
programme and Employer’s objectives.
Re-programming
On many projects a re-programming exercise is necessary
to bring the project back on time and within budget. It
is often beneficial to appoint an external specialist organisation
to carry out this exercise to provide a “fresh look” at an ongoing project.
RELATED CASE STUDIES
New
City Centre Development: Re-programming
New
Laboratory; M.& E.Services: Detailed Planning & Programming.
FURTHER INFORMATION & CONTACT
info@gibsonconsulting.co.uk
Gibson Consulting, 3 The Quadrant, Coventry CV1 2DY
Tel: +44 (0)24 7624 3607 Fax: +44 (0)24
7624 3608
back to the top
|